May 19, 2015

Paving Progress

Finally starting the concrete flatwork (steps, walkways, driveway).  You can see the wood forms on the ground where the walkway will be poured.

The subcontractor was scheduled for 2 1/2 months ago, but only now has arrived, despite constant attempts on our part to get them here.  A source of major stress and consternation.

Lisa and the cat inspect the formwork.