November 07, 2014

Ceiling Fan Mount



The old question:  how to mount a ceiling fan on the ridge of a vaulted ceiling?

Battle of the Radios

We had a situation the other day: 4 radios at once, battling for supremacy.

80's music inside,
Latino music on the roof,
Rock in the front,
and Jazz in the back.

Overheard on the Jobsite:

"...and every time _____ got drunk, _____ would play Pat Benatar at top volume and sing every word"

November 04, 2014

Carport Roof

Membrane roof installation on the Carport/Entry roof canopy.  With built-in gutter.
The first of the roofing was completed today.  It is a low-slope roof on top of the carport and entry canopy.  At some point in the future, lightweight soil and plants will cover this, creating a garden roof.

Sunday (Monday) Progress Update

What are these?
In the last week, many things have happened, but which don't lend themselves to photographs.

October 30, 2014

Heating the Breakfast Nook

Routered Subfloor
This piece of plywood will be the subfloor for the breakfast nook seen beyond. 

I'm using a router to cut channels in the 1 1/8" thick plywood.  Radiant floor tubing will be placed in these channels to make sure the breakfast nook is nice and cosy in the winter.

A piece of tubing is inside the channels on the left, making sure the bends are workable.

The finished flooring (fir) will cover this tubing, and insulation below it will direct the heat upwards.

A first glimpse of the large awning window (custom from Versatile) can be seen beyond.  Didn't get a chance to photograph the install.  Now it huddles under a tarp until I get protective finish on it.

A straightedge guides the router for the straight cuts, but the curves are freehand.  A little bit of wonkiness is acceptable, I hope. 

October 27, 2014

Exterior Assembly Work

Steel Window Box, Exterior Insulation
Today's work covered a few milestones:
- The first of the steel window boxes was installed
- The bottom-of-wall metal drip flashing and bug screen was completed
- The first of the exterior rockwool insulation was installed.

October 25, 2014

Tales from the Jobsite

This evening we had wind gusts approaching 50 mph.
Out on the deck trying to further ballast down the billowing tarp, I was locked out of the house when the wind slammed the door behind me.  (Predictable? Doh.)
The exterior latch handle has yet to be installed.

The deck is on the second floor.

Feeling foolish, I considered my ninja skills, or lack-there-of, for a climb down two stories in the rain.

As luck would have it, I realized there was still a ladder leaning against the east canopy, and I was able to make the much less dangerous lateral clamber over to it.

I might just leave that ladder there for a while longer.

More Bathtub

Wait, what?
Just had to share this shot of the bathtub install. 

A bit of on-the-fly awkward adjustment process.

October 23, 2014

Overheard at the Jobsite

"Well I don't have a magic wand, so what am I supposed to do about it?"

Feelin' Sill-y

The first steel sills installed
Remember those steel sills and copings here that I was painting?

Today the weather broke long enough for me to install the first run of them along the master bedroom window 'slot'.

Duct, Duct, Grille

Duct Spaghetti
As part of the Mechanical System rough-in, the ERV has been installed.